We are testing a profit center reorganization. Sap told me that Service PO are supported as long as the planned acount assignment and the actual account assignment isn't different. SAP note 2190104 advises to check that. I'm struggling to create a quickview joining these two tables with EKKO, EKPO and so on. But it doen't work.
Can anybody tell me how to join EKSN and EKKN? I have checked the link on Wiki regarding Service account assignment, but still it's not clear to me.
Thank you!
Joachim
Dear Joachim,
Agreed with Prasoon, You need to pass SES number form ESKN to ESSR, where you get PO number than EKKN and EKPO linked by the PO numer, item number.
Best Regards
Mohsin Abbasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You may pass the SES number from ESKN to ESSR and get PO number & item number. Link EKKN and EKPO using PO number, item number and account assignment sequence number.
Also refer the wiki: Service Package - ERP SCM - SCN Wiki
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.