on 02-13-2016 8:39 AM
Dear colleagues
I have done KSPP in previous period.
How can I find the sources of activities from PP?
I would like to know activity quantities from particular materials and plant.
Thanks for you responses.
Hi Alexander
The Source is the Plan Data that you load in COPA planning or in SOP or in LTP (Long Term Planning)
The Plan data (x) Routing Qty will give you the result of Planned Activity Qty
Regards
Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm not quite sure if I understand your requirement correctly. But maybe in MS05 you will find the information you are looking for.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Michael.
I'm not sure that someone didn't change plan orders after I had done KSPP.
For example I had done KSPP in December 2014 for all periods 2015 but someone changed plan orders in March 2015 for January 2015 and after that I can't see why I have these activity quantities in cost centres.
Best regards,
Alexander.
Hello Alexander,
Please check the notes below which should be helpful.
41621 - KSPP: Preconditions for transferring activities
1889852 Transaction code KSPP returns multiple periods for Activity Scheduled.
1891139 Transaction code KSPP returns wrong Activity Quantity
Best regards,
Jason
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.