operations on order

raju_123
Participant
0 Kudos

Hi, In my process order i have 0010, 0020, 0030, 0040, 0050, 0060 operations/ phases. 0010,30,50 are operations and 20,40,60 are phases. in order cor3  operations screen i can see all 3 phases latest start dates and time are same. how to set after completion of phase 20, phase 40 should start. after completion of 40, phase 60 should start. please advise.

Accepted Solutions (0)

Answers (1)

Answers (1)

marianoc
Active Contributor
0 Kudos

Hello Raju,

You can control the sequence of your operations at the Confirmation.

Go to t-code OPK4, and check the options that you have for Operation Sequence.


Check of operation sequence in order

Defines whether a system message is to be issued when the operation sequence is not adhered to and if so, which type of message. This key only applies to confirmations at operation level.


Dependencies

To find out whether the operation sequence has been adhered to, the following checks are carried out: Have preceding operations already been confirmed? Does the confirmed yield from the preceding operations exceed the total confirmed quantity of the operation to be confirmed?

Note that for planning, the operations are always plan in sequence, except you have overlapping or an alternative sequence.

Kind Regards,

Mariano