on 04-26-2016 10:26 AM
Dear All,
I am doing a support project,
When i enter into a PPB screen , I can able to see the Project id, Wbs Name Etc.
But when i created a work center and assigned to an activity . i couldnt able to see the discription of the WBS & network in the PPB.
I had done all the checks like , In Project screen all elements are checked in options,In PPB screen all elements are checked in, PPB profile is standard one is renamed as "XX"
I believe that this issue is not with missing customizing.
Kindly help me in this issue.
Regards,
Mahesh
Hi all,
I was facing same issue in my system on having GUI740. Issue got resolved by upgrading to latest patch 3 .
So any of you facing same issue please upgrade to patch 3 for GUI740 and for GUI730 to patch 11.
Regards,
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Currently i am out of the Problem but i need to fix this issue.
When i open the same project in another Computer .
In same sand box with their user id i can able to see the WBS names.
Now i will cross check will give the feed back to you all soon.
As You all said it might be the Basis Problem.
Regards,
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
Well, I replicated your problem, check below screenshot
Then blank lines are the WBS element area.
Now, you can go to below link in SPRO and see if you the color setting is White
SPRO - SAP NetWeaver - Application Server - Frontend Services - Bar chart - Define fields
To select the correct field, you need to compare the Graphic profile assigned to your PPB profile. As per the information you provided, it is SAPPS_PSST00
In the configuration, check the Form PSST00 and Below as per screenshot
Open this form and check the colour
This should be the combination of your back ground color setup in your user setting for the planning board.
This is just an idea on how the system is behaving, but not sure whether this is the actual issue for your case. Seeing all these setup, it looks like the issue is related to graphic profile or font color setup. Try to change the color and play around, you should be able to fix it.
Also, check for other users, whether they are able to see the text, in such case, check the user settings saved in the planning board assistant. That should fix your issue.
Regards
Terence
Hi Mahesh,
Open the project in CJ2B
Go to PPB assistant
Change the color, fox example, change the color from Black to White in Project Definition
Now Save
Open the project to see whether the changes are updated
Have you tried to check with any other user, whether they have the same issue ?
Finally if nothing works, OSS needs to be raised
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you check the description field is available on display section, if not bring that field through change layout option on PPB. Hope this should help.
THanks
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
I guess, below is what missing in your system
Recently i have seen many posts on the same issue, did you tried by selecting different profile.
Any recent upgrade done in your system ?
Refer below Note
501924 - CJ2B: Missing texts in IMG bar chart field definitions
You need to compare the data in the note to table TFATT
Regards
Terence
Message was edited by: Maria Terence
Dear Terence,
you are absolutely correct.
As i told, earlier in this thread. Before i touch this system my client can see the PPB with WBS,Activities...Etc.
But when i touch the system for rectifying the scheduling error . I created a work centre and its relevant parameters are added to the activity. then scheduling is working fine in project screen (CJ20N)
Form there i am entering into the PPB then discription of the WBS,activity cant be seen.
All the standard parameters only i am maintaing like PPB profile(SAP std) in Project profile.
As per my analysis this problem is due to gantchart.
Sry for the inconvenience, I am not having the access to configuration changes.
I can view only.
Regards,
Mahesh
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.