We are trying to evaluate and use the SAP R/3 rebates functionality and have a requirement to settle rebates partially every month without needing the user to manually trigger the settlement processes. Here is the scenario.

1) The rebate agreement is valid from Jan to Dec

2)  A partial settlement should run sometime during the 2nd week of the every month

3) While making the settlement, invoices created or amount accrued for the previous month only should be settled. Invoice or amount accrued for the first two weeks of next month should not be considered.

eg) Amount accrued in Jan will be settled mid Feb and amount accrued in Feb should be settled in mid Mar.

4) The partial settlement should happen automatically without the need of an user interaction.

Can you let me know how this can be achieved in SAP R/3 ECC 6.0.Looking forward for your suggestions.

Regards,

Pratheb

Accepted Solutions (0)

Answers (1)

Answers (1)

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

Did you check the T.code- VB(7

you can run this programme in the background under scheduled Job with SM36