I have created an order in which I have mentioned start date with forward scheduling and priority type- high (Rel. end- days).
According to it, system should update the basic finish date but system is updating finish date same as basic date.
Kindly provide the solution.
Thanks & regards,
Ashish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashish,
What is your setting in OPU7?
Based on Adjust date configuration, Basic start and finish dates are proposed.
If you want the dates to be updated from operation, you need to make you maintain hours for each operation to determine the exact start and finish dates
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have changed the configuration to "Do not adjust basic dates, dep. rqmnts to operation dates". and basic start date & finish date are now adjustable but schedule start date & finish date are current dates instead of same as basic start & finish dates.
For example: Today I have created an order with basic start date 01.04.2016 and basic finish date 20.04.2016. Post release this order, System shows schedule start & finish date as 28.04.2016. Logically system shows schedule start date : 01.04.2016.
My client need to punch back dated order which may be external services.
Please provide the solution.