on 04-28-2016 4:36 PM
Hi All,
For the first time, we implemented Parallel processing, where the scrap quantity is entered in one of the Sequence.
and the scrap is confirmed.
But when we execute KKS2 there is an error message KV161 " WIP or scrap calculation for parallel operation sequence not possible"
As per the SAP procedure
If you want to calculate scrap or WIP, donot define parallel sequences.
Can any one guide how to fetch the scrap quantity in parallel processing.
Thanks,
Jagadish
Hi Jagadish,
Please implement note 1601599. With the attached correction it is possible to calculate scrap variances and WIP in case of parallel sequences in case the message KV161 has been switched off in the according message control (OPR4_KKS, OPR4_KKS1, OPR4_KKA, OPR4_KKP).
In order to be able to calculate WIP and scrap variances in spite of parallel operations you need to switch off the message KV161 completely in transaction OPR4_KKA and in transaction OPR4_KKS (message type " " or "*") as described in note 1601599.
However, in the calculation only the standard sequence is taken into account. Parallel sequences are not taken into account.
Thanks,
Robin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.