Hi Experts,
I would like to know about Maintenance Revision. So please explain maintenance revision with real time scenario & a step by step business process which involve maintenance revision.
Thanks& Regards,
rakesh Kushwaha
Practical use:
After creating a Revision (8char label) through tcode OIOB which has StDt/EnDt and Times, you can assign the same to multiple Notifications or Orders in mass. This facilitates you to search such Notifications and Orders by Revision label. Means when you want to plan few jobs on a particular Date then Create a Revision and assign that Revision to all such Notifications and/or Orders.
How you assign a Revision to several Notifications in mass.
In IW28 list output , select Notification lines you want to assign a Revision and go to menu Notification > Assign Revision and do it.
Similarly in IW38 you can do it for Orders
Order > Revision > Assign Revision
After doing so you can list such Notifications and Orders by giving the Revision label in the respective (IW28 or IW38) Selection screens.
After finishing such jobs, you can mark this Revision as Revision completed in OIOB.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This link starts with the Definition and explains everything you wanted. Revision - Maintenance Planning - SAP Library
The first line itself explains its application. If you need any specific doubts you may revert.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.