on 05-05-2016 6:49 AM
Dear Expertes
we create reservation at operation WBS ( as a Activity).We run project based MRP through MD51.
My Issue is "when the WBS In project & sales order is same then system club requirement of project & sales order if it is different then why sales order not create planned order" ?.
Refer screen shot 1 : Where WBS in project and sales order is different .
Reservation =300, Sales order =30, Stock =25 . Planned order =300-25 =275
Refer screen shot 2 : where WBS in project & sales order is same. So system is clubbing requirement
Ex :
Reservation =300, Sales order =30, Stock =25 . Planned order = 300+30-25=305
Hello,
In material master MRP 4 view what is the setting for Individual/coll. indicator?
Transaction MD04 exception messages 30' from the rescheduling check can also be used to determine receipt elements that are not covered.
POlease refer,
What is rescheduling and how does it work - ERP Manufacturing (PP) - SCN Wiki
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
The problem here is that the sales order is linked to a different project stock on the first screenshot.
On the second one, both the reservation and the sales order are linked to the same project, so they are "clubbed".
You should ensure that the same project is used on the sales order and reservation account assignment.
BR
Caetano
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.