on 05-05-2016 11:48 AM
Dear All,
In the work center A (Machine), we defined that the number of machines available is 5.
This will cause the available capacity become 5 times.
During confirmation, we want to confirm accordingly with the machine number, for example
300 KG from machine A
200 KG from machine B
etc
How to do it in the SAP PP?
We are using PP Discrete.
Any help is appreciated
Thanks,
Steve
Hello,
In CO11N you can have individual capacity split, for that define confirmation profile in OPK0
Header area 110
You can use BAdi WORKORDER_CONFIRM method method INDIVIDUAL_CAPACITY
With this method, you can determine an individual capacity and predefine values for the corresponding fields in the confirmation. After this, you can post the confirmation with reference to the predefined individual capacity refer SAP note 1841605 - BAdI WORKORDER_CONFIRM: Predefine individual capacity.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.