Machine / Production Line in Confirmation

Former Member
0 Kudos

Dear All,

In the work center A (Machine), we defined that the number of machines available is 5.

This will cause the available capacity become 5 times.

During confirmation, we want to confirm accordingly with the machine number, for example

300 KG from machine A

200 KG from machine B

etc

How to do it in the SAP PP?

We are using PP Discrete.

Any help is appreciated

Thanks,

Steve

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

In CO11N you can have  individual capacity split, for that define confirmation profile in OPK0

Header area 110

You can use BAdi  WORKORDER_CONFIRM method method INDIVIDUAL_CAPACITY

With this method, you can determine an individual capacity and predefine values for the corresponding fields in the confirmation. After this, you can post the confirmation with reference to the predefined individual capacity refer SAP note  1841605 - BAdI WORKORDER_CONFIRM: Predefine individual capacity.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks Brahmankar,

I will explore this solution.

Best Regards,

Steve