cancel
Showing results for 
Search instead for 
Did you mean: 

SAP Time managementSchema-operation for original DWS in all cases

former_member682742
Participant
0 Kudos

Hi there,

VASRTDAYPG operation picks up the current daily work schedule (i.e. original if not substituted and substituted one if substitution is done).

Which operation is available for always picking up the original daily work schedule in schema, even when the original schedule is substituted.

Any help is appreciated.

Thanks!

Gajanan

Accepted Solutions (0)

Answers (1)

Answers (1)

jagan_gunja
Active Contributor
0 Kudos

HRS=S provides DWS working hrs with any substitution if entered for the day.

HRS=U ignores any such substitution

See the main help text enclosed for the HRS operation

Also note VARST is a decision operation where as HRS with ? is a decision operation.