Dear Experts,
I need clarification on Purchase Requisitions in opening period parameter in MD02/MD03.
Suppose for example, opening period (SMK) = 14 and delivery time = 30 days.
What is the horizon for purchase requisitions? Is it material master opening period alone = 14 days? or opening period + planned delivery time = 43 days?
Regards,
Thomas
Hello,
Opening period is maintained in configuration of Schedule Margin Key in your case it is14 days.
Refer SAP help documents
Define floats (scheduling margin key)
Creation Indicator - Carrying Out the Planning Run (PP-MRP-PR) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
The opening period for the planned order represents the number of workdays that are subtracted from the order start date in order to determine the order opening date from current date of MRP run
Backward scheduling
Mtl. Av. Date = Requirement date - GR processing time - PDT - Planned processing time - Opening period
Forward scheduling:
Today's date + Opening period + Planned processing time + PDT = Delivery date
If requirement lies in the opening period and you have an option of “creation of purchase requisitions in the opening period system create procurement proposal in opening period
Best Regards,
R.Brahmanlkar
Hello
Kindly refer to SAP note 206666 - MRP control parameters during planning.
An opening period "0" means , with indicator "Create req. order from 2" , PRs can be created only if the opening date is same as planning date.
Now if opening period is 14 days , use MRP controller as "1" - Create PR.
Hope it answers your doubt.
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Thomas
The opening period is calculated with the value from the scheduling margin key only. As explained on note 23922, an opening period of 0 days means that, together with the indicator "Create req. order" from "2", purchase requisitions can be created only if the opening date is the same as the planning date.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.