If the PO is delivered completely in SNC , can we open again same PO and create new ASN for open quantity.
Thanks,
Karunakar M
Hi Karunakar,
Once PO is confirmed and delivered completely we cant edit in SNC system.in ECC only we can edit
the PO in this case.
Thanks&Regards,
Vishnu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Karunakar,
Let me repeat my understanding:
1- You are creating a PO in ECC as 100 Cases and then confirming as a Supplier in SNC as 100 Cases.
2- You are creating an ASN referring to this PO in SNC as 100 Cases.
At this point, you would like to create another ASN for 50 Cases in SNC referring to the initial PO. This means sending 150 Cases of goods for a PO which is shared as 100 Cases.
Does this understanding correct ?
If that is the case and if you keep the delivery tolerance high in the info records then it is possible.
Else lets talk...
Regards,
Selim Batur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Selim,
Below is our scenario
Our expectation is - The Due quantity in item should be updated with '100' as due quantity in SNC web UI, which is not happening. We need the Due qty to be updated, as we need new ASN to be
created in the system for the returned qty.
So when we create a new ASN after return delivery, the system is giving error message 'ASN Item AUTOMATIC ID / 000001: notified qty 100.000000 is greater than qty due 0.000000 (tolerance: 0.000000)'
Kindly help.
Regards,