on 06-17-2016 6:27 AM
Dear EM Experts,
I have a question about EM alerts. We have alerts (delayed alerts) configured for the events. But the alerts job (/SAPTRX/EE_MONITOR) is OFF.
Now we want to run & schedule the job /SAPTRX/EE_MONITOR. But last time, when we ran this then it took all the overdue alters till date and sent hundreds of emails to our carriers.
Do we have a best practice to achieve this with sending too many emails?
Regards,
Ashish
Hi Ashish,
Try using /SAPTRX/EE_MONITOR_PACK with your event code and dates as selection and see if it works for you. Do it in non-prod environment first. Other than that, I am guessing you have to customize your /SAPTRX/EE_MONITOR to process only a specific EH and Events.
Thanks,
Vishnu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When you save the variant (to be used in the job) you need to use standard dynamic date calculation available for all date fields in selection variants. See below...
To dynamically determine Date From and Date To save the variant as follows:
Date From is a Dynamic Date variable = Current Date - 1 and Date To is a Dynamic Date variable for Current Date. This gives you a moving window of yesterday and today... Standard functionality
Thanks
Kevin
Hi Ashish,
The below document provides different expected event monitors in SAP EM and selection options. Check your system which SAP EM version and apply SAP OSS notes appropriately if you don't find the EE monitor.
Regards
GGOPII
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.