on 06-21-2016 8:58 AM
Hi All
Valid Tlane is available between two plant but not appear or consider while creating the order in product view.
Getting below message in log
No transportation lane/procurement relationship for prod.xxxxxxxxx loc. yyyy
Message no. /SAPAPO/RRP013
Diagnosis
You have maintained external procurement as procurement type for product XXXXXXX in location YYYY.
System Response
The system could neither find a valid transportation lane nor an external procurement relationship
Why system does show or consider valid tlane ? Please advice
rgds
SDB
Solution - Mot was not maintained product wise otherwise "all product product' should be active in MOT