on 06-23-2016 1:48 PM
I accidentally checked in activity that demage the project.
Is there a way to undo/cancel the last activity and revert to one activity before ?
Thanks,
Faniel
Hi,
Or: if you know what changes exactly "damaged" the project and it is not a big effort to remove it then just create a new activity in which you eliminate the problem.
An already activated activity cannot be reverted.
Best Regards,
Ervin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Faniel,
this is not quite easy. You will have to resynch to the older state via DTR perspective. Then copy the files from the project with the older state on filesystem. Synch the project to current broken state and replace the files with the copied ones in filesystem. Then refresh your project and create a new dtr activity with the changes and check it in.
Hope this helps,
Tobias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.