10-01-2007 11:42 AM
hi all,
go with cj03 transaction,give the project definiton(p:04423) or wbs element(p:04423-ca) in the initial screen and then go with the display. then we get number of wbs element, from that select any one of the wbs element and go with settlement rule button below. you will go into another screen in that we see some rule. i just want to know how this rule is created .reply me asap.
thanks in advance,
Rama.
10-02-2007 8:30 AM
Hi Rama ,
Settlement Rule nothing like defining to which G/L,Profit,Cost Center these costs goes to ?
Regards
Peram
05-14-2008 3:39 PM
Do you have any idea how to exclude settlement costs in CN41? My CN41 has costs duplicated when I compare to CJI3. The OSS Note 51971 was applied.
10-02-2007 8:30 AM
Hi,
Please use search facility in standard SAP Help for this kind of general questions as the first try. Anyway:
Here is the link: <a href="http://help.sap.com/erp2005_ehp_02/helpdata/en/23/52298e099b11d2add30000e8a6353a/content.htm">PS Settlement rules</a> (Click "red arrows" to enhance search...)
In IMG, use the follwoing path (ERP 6.0 system): Trans SPRO -> Project System -> Costs -> Automatic and Periodic Allocations -> Settlement -> All nodes below here.
The settlement rule is assigned to a project profile (trans OPSA) and when a project is created this profile is read and the settlement rule is createad for the project. User then must fill in values in the settlement rule so that the settlement run can be run at period end closing.
Reward if useful so others can benefit from this answer.
Regards, Johan
05-15-2008 5:28 AM
Hi,
Settlement rule can be maintained manually or generated automatically. For automatic generation you need to deifne Settlement Strategy in Project profile. Later execution of tcode CJB2 results in generation of settlement rules.
Regards