cancel
Showing results for 
Search instead for 
Did you mean: 

LB10:

Former Member
0 Kudos

Hi,

After I confirmed the process order, the components was automatically perform 261 mvt. Then after that I did LB10 but only 1 components performed Transfer Order and give transfer Requirement Number. I checked LT24 but the other components does not have TR Number? What might be the cause that the other components failed the Transfer Order?

Thanks in advanced.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello, Ellen

It is not clear if you are trying to move the components to supply area after the Goods Issue ??

How is the Interface WM-PP set ?

You are using release orders parts, crate parts, etc. ) ? Or tell us how are your control cycle.

Regards

Dario

Answers (0)