on 11-14-2007 10:53 AM
Hi,
In BPS, for Copy planning function we have an option of :
1)Overwrite existing values
2)Add to Exisiting values.
I couldn't fine the same in IP. even in the to parameters section.
What is the standard behaviour of Copy planning function in IP.
Rgds
In BPS that was an added feature. IP overwrites the exiciting values for the same keys.
Ravi Thothadri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So quick answer, in IP it standard overwrites. If you want a copy function which adds, then you have to create a Fox.
Regards,
Juriaan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
You dont have the below in IP. Please check the link for Copy funtion in IP.
1)Overwrite existing values
2)Add to Exisiting values.
http://help.sap.com/saphelp_nw04s/helpdata/en/43/548bafbc0f357ee10000000a11466f/frameset.htm
Regards,
-N-
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I just checked BPS of BI 7.0, there is no overwritten or add choice anymore.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.