on 01-18-2008 7:46 AM
Hi, everybody
i have already created a production order, but when i Receipt from production, an error appear" Referenced production oder status should be "released"".
i dont undersatnd it.
Mr Tian Le,
Go To that particular production order and change the status of the production order to Released only then the sytem allows you to create the production.
Please reward points.
Nagesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the Production Process the first 2 steps are
Create the Production Order
Then Release the Production Order by changing the Production Order Status from PLANNED to RELEASED.
This is the message you are getting. So go to the Prod Order and change the status to RELEASED and then try
Suda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.