Dear All,
I need to change the factory calendar and i am working on 4.6C. This is the first time i am doing it. Can any body please give me the procedure as to how to go abt it.
please help.
With Regards
Ranjith Singh A.K.
Hi Ranjith,
I didn't remember the way, but go in SPRO, and use the search option for the word "calendar" or "factory calendar".
you will find quickly
Rgd
Frédéric
Hi,
Thanx for the reply but i am not able to find the date to change it
Hi,
can start directly the transaction <b>SCAL</b>.
Perhaps this link for 46c helps you to understand the concept:
http://help.sap.com/saphelp_46c/helpdata/en/35/6f3ed1268b2239e10000009b38f984/content.htm
Regards,
Stefan
Message was edited by: Stefan Gerschler
Hi,
Thanx for the Link. I was able to add the New Holiday in the but it is not getting linked to The Factory Calendar.
Can u please tell me where to see this.
Ranjith Singh
You will use SCAL for all calendars, factory or holiday. Once you define your holiday calendar, you will then go to your factory calendar and assign this holiday calendar to it.
What do you mean by holiday is not linked to the factory calendar?
Srinivas
Hi,
Please follow the below given link on how you can create a new factory calendar as well as how you can change the factory calendar in SAP.
http://www.learnsaptips.com/2012/08/factory-calendar-maintanance-in-sap.html
Hope it helps you!
Best regards,
Simon