on 04-04-2008 12:10 PM
Hi Experts,
How to add Personnel numbers (maintained against Workcenters) to the Task Lists operations. We have Maintenance plans with TL, and want to have the Personnel No defaulted when the Maintenance order is generated.
Krishnan
Goto To change option in maintenace rask list. Select your task list and than click on operation. There you will find Internal tab. click on that. Now u can place personal number if that person is mapped HR mini master.
Hope you will find it.
Kaushal Rai
Edited by: Kaushal Rai on Apr 8, 2008 9:11 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
i think it is not possible to add Perssonel no in the Task list
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.