Can anybody explain me what is difeerence betweem PS and MM..? clearly.
In PS also some MM activity has to happen, how we can map in SAP.
Thanks
sap-mm
PS-- Mile stones are defined in PS, and it will not have any std Org Structure, you can define your own Org Structure basing on your requirement.
from PS you can create MMD & also the PR.
In MM we use WBS or Network as account assignment for Procurement as well as for Goods issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for ur quick response.
See i wil tel u my client scenario .
My client doing new projects, for that projects they will do procurement and contracts only for projects eg,civil construction.
whether i want to do any configuration for MM in Project related works or PS wil take care about this..?
Can u explain me who wil do the customisatyion part of PS and MM in new projects..?
Thanks
sap-mm
Hi
Related to the PS Project systems Consultant has to take care of the Customizing activity.
From MM perspective to integarte with PS there is very little Customizing required. But for proper reporting you can create
Projects relevant purchasing organization & purchase groups for Project procurement, new PR, PO document types to identify the PS procurements.
In PS the major customizing activites are
Project coding mask for WBS elements,
Project Profile, Network Profile, Budget profiles, Activity Profiles,
Scheduling activities,
Value Categories, Planned Costs, Budgeting ,
Progress tracking, Procurement activities,
Thanks & Regards
Kishore
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.