Confirmation Problem

Former Member
0 Kudos

Hi friends,

My process order contains 5 operations, When I am doing the final confirmation for the 1st operation my whole order is getting the status CNF which should be PCNF since remaining 4 operation are still in REL state.

Pl. give your valueable suggetions for the above issue.

Regards,

Amit Shirsath.

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hy Amit,

Pls give status of Order and Operations, which helps to find out reason behind this problem more easier.

Regards,

Dhaval

Former Member
0 Kudos

Hi Dhaval

The staus of order when I am doing the final confirmation for the 1st operation is as follows,

REL Released

CNF Confirmed

PRC Pre-costed

CSER Error in cost calculation

BCRQ Order to be handled in batches

BRRQ Batch record required

MANC Mat.availability not checked

SETC Settlement rule created

Staus of the 1st operation is

CNF REL.

Regards,

Amit.

dhaval_choksi3
Active Contributor
0 Kudos

Hy Amit,

I think cause behind this is control key attched in the rest of the operations.Just check confirmation parameter in that Control key is set 3 (Confirmation not possible) or 2(Confirmation possible but not necessary).

Regards,

Dhaval

Edited by: Dhaval on Jun 17, 2008 12:53 PM

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Which operation you are confirming......Please check whether you are confirming the last operation or wt and it must be having control key with milestone confirmation,

Regards,

Anand

Former Member
0 Kudos

Hi ,

Plz check control key for the last operation .for it milestone confirmation should be there .

check & revert

abhay