Pre Go-Live checklist

Former Member
0 Kudos

Hello All

We are soon going live with the integration of thirdparty CRM system with our SAP system . I would liek to know from all the experts the tasks and checklists that need ot be performed before going live .

Our scenarios are all involving MAster and sales data, and all scenarios are IDOC/BAPI to&from SOAP services. All of your sugestions are welcome ,

Thank you

Sudheer

Accepted Solutions (1)

Accepted Solutions (1)

prateek
Active Contributor
0 Kudos

The activities are largely dependent on the landscape. A typical environment will have atleast these tasks in place

- First of all u should check the readiness of ur sender and receiver systems. e.g. all the live data should be loaded and present in the production R3 system.

- Transport mechanism to the production environment is finalized

- Then a fail-over mechanism is identified and finalized

Regards,

Prateek

Former Member
0 Kudos

Hi Prateek ,

Does Fail over mechanism means , Exception/Error handling ? Or did u mean something else.

prateek
Active Contributor
0 Kudos

It mean that if the go-live fails, how should u proceed. By just deactivating the scenario or also starting the earlier message flow, if any.

Regards,

Prateek

Answers (3)

Answers (3)

Former Member
0 Kudos

Contact SAP about your SAP GoingLive Check !

Guides You to a Smooth Start of Production and Technically Robust Operations

The SAP GoingLive Check safeguards your SAP solution to a smooth start of production, which is the final milestone of a successful implementation project. This proactive service mitigates the risks that arise from non-optimal system and business process configuration. It ensures a technically robust operation from the beginning and therefore protects your business.

During this service, certified SAP service consultants check the solution in a standardized procedure and give recommendations ensuring optimal performance and system availability for the core business processes. The SAP GoingLive Check is a remote service that is performed in SAP Solution Manager and uses the end-to-end root cause analysis tools. The results are delivered in a detailed service report including an action plan.

Depending on your SAP solution and contract type, you will receive a customized GoingLive Service portfolio tailored to your needs. The portfolio consists of up to three service sessions: analysis, optimization, and verification. The delivery of the individual sessions takes place at key phases in the implementation project:

Analysis session: checks the configuration of the SAP system, operating system and database. The session is scheduled a minimum four weeks before your start of production

Optimization session (optional): optimizes the response times of the core business transactions and is scheduled normally two weeks before your start of production depending on the availability of the productive data

Verification session: verifies the smooth operation and performance of the productive environment and is scheduled six to eight weeks after start of production

http://service.sap.com/~form/sapnet?_SHORTKEY=01100035870000707856&;

Also check: https://service.sap.com/~sapidb/012006153200000920262007E/Readiness_Check_Version4.pdf

Former Member
0 Kudos

There is a XI readiness check - (SAP Note: 817920)

Also the install and configuration guides have a checklist and step by step post install directions

Check this XI configuration Guide-

https://websmp102.sap-ag.de/~sapidb/011000358700001697502004E.PDF

try this link: https://websmp208.sap-ag.de/~sapidb/012003146900000134402005E.ITF

The note is available on the service marketplace.

Additional there is an Admin Check Guide available as attachement to note 884865, which might also be useful.

Former Member
0 Kudos

hi,

See this link:

/people/jayakrishnan.nair/blog/2006/07/24/building-your-xi-environments

Thanks,

Vijaya

Former Member
0 Kudos

hi,

check these too..

Following links will help solving your questions

/people/sravya.talanki2/blog/2005/11/02/overview-of-transition-from-dev-to-qa-in-xi

/people/community.user/blog/2007/01/18/steps-for-a-sound-footing-in-your-xi-project

https://websmp104.sap-ag.de/~sapdownload/011000358700001684302005E/HowToSLDandXI.pdf

http://help.sap.com/saphelp_nw2004s/helpdata/en/93/a3a74046033913e10000000a155106/frameset.htm

Thanks,

Vijaya