Hi Experts,
With out Controlling module configurations, can we Configure PP module directly?
Thanks
Chandra
Hi,
Yes you can configure PP with out CO but you will not get Product Costing results for the materials used.
You will not be able to link Activities, Cost Centers, Over Heads which are production activities.
Cost Analyisis for the Order will not be possible.
To say in brief Cost related entries or break up is not possible if CO is not implemented.
Regards
Balaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.