Dear Expert ,
I maintain in material master float before and after production
When i rescheduling in house production in routing and display the result i found the time for float is calculated in Interoperation time
And I as i know Scheduled start & Scheduled finish determined the production dates only & FBefProd is time between basic start and Scheduled start and FAftProd is the time between Scheduled finish date & basic finish date
Why he put it there at the time it's not actually maintained in production date ?
Regards
Rami
Dear,
In the routing, click on scheduling result push button,
Here you can see how this interoperatioon time is calculated
how much is Float before and after production.
example-
schedule margine key - 001
float before production - 2 day
Float after production - 1 days
Routing data- for 1 qty - 24 hrs
After you schedule in routing and see the details of scheduling result, the following result
Basic start date - 30.11.2008
Basic finish date - 03.12.2008.
Scheduled start date - 02.12.2008
Scheduled finish date - 02.12.2008.
base qty - 1 TO
Processing time - 1 day
interoperation time - 3(all inclding floats)
Total inhouse production time - 4 days
Now repeat it for 2 qty, results are as below
Basic start date - 30.11.2008
Basic finish date - 04.12.2008.
Scheduled start date - 02.12.2008
Scheduled finish date - 03.12.2008.
base qty - 2 TO
Processing time - 2 day
interoperation time - 3(all inclding floats)
Total inhouse production time - 5 days
I hope you got the idea.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
10 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.