Scheduling Margin key ( Float before production - Float after production)

former_member182449
Participant
0 Kudos

Dear Expert ,

I maintain in material master float before and after production

When i rescheduling in house production in routing and display the result i found the time for float is calculated in Interoperation time

And I as i know Scheduled start & Scheduled finish determined the production dates only & FBefProd is time between basic start and Scheduled start and FAftProd is the time between Scheduled finish date & basic finish date

Why he put it there at the time it's not actually maintained in production date ?

Regards

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

In the routing, click on scheduling result push button,

Here you can see how this interoperatioon time is calculated

how much is Float before and after production.

example-

schedule margine key - 001

float before production - 2 day

Float after production - 1 days

Routing data- for 1 qty - 24 hrs

After you schedule in routing and see the details of scheduling result, the following result

Basic start date - 30.11.2008

Basic finish date - 03.12.2008.

Scheduled start date - 02.12.2008

Scheduled finish date - 02.12.2008.

base qty - 1 TO

Processing time - 1 day

interoperation time - 3(all inclding floats)

Total inhouse production time - 4 days

Now repeat it for 2 qty, results are as below

Basic start date - 30.11.2008

Basic finish date - 04.12.2008.

Scheduled start date - 02.12.2008

Scheduled finish date - 03.12.2008.

base qty - 2 TO

Processing time - 2 day

interoperation time - 3(all inclding floats)

Total inhouse production time - 5 days

I hope you got the idea.