Hello All,

I am creating the public holidays for the year 2009 and assigned to holiday calendar. When I try to open any material in MD04 it is throwing the below message. Issues is very vital please respond.

Invalid factory calendar or error in the factory calendar 29.12.2008

Message no. 61063

Diagnosis

This problem is caused by a setting error.

Procedure

Check the various periods of the factory calendar in customizing. If you do not have the necessary authorization to do this, inform your system administrator.

Regards,

Ganesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

check the calender assinged to the plant.

Enterprise Structure=-->Definition->Logistics - General->Define, copy, delete, check plant

-ashok