on 10-09-2009 4:46 AM
Hi all,
i run the MD02 and it is showing schedule in MD04 but problem is that it is showing 0 quantity in ME2M as still to be delivered.
can anyone plz let us know why it is showing 0 quantity in ME2M in still to be delivered.
Regards.
saurabh.
Hello ,
Check the MRP element if its for PchOrder ( i.e material is required ) or ShipNt ( Inbound Delivery ) in Md04 for the material , plant combinations .
In both the above case , it will show that material is expected in the system . Unless the GR is done , it will show that material is to be delivered . Once you receive the material it will show the material is delivered .
Please let me know if this is what information you are looking for.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.