Hi all,

i run the MD02 and it is showing schedule in MD04 but problem is that it is showing 0 quantity in ME2M as still to be delivered.

can anyone plz let us know why it is showing 0 quantity in ME2M in still to be delivered.

Regards.

saurabh.

Accepted Solutions (0)

Answers (1)

Answers (1)

lawrei99
Participant
0 Kudos

Hello ,

Check the MRP element if its for PchOrder ( i.e material is required ) or ShipNt ( Inbound Delivery ) in Md04 for the material , plant combinations .

In both the above case , it will show that material is expected in the system . Unless the GR is done , it will show that material is to be delivered . Once you receive the material it will show the material is delivered .

Please let me know if this is what information you are looking for.

Regards

former_member1284402
Participant
0 Kudos

hii thanks for reply...

actually i have run the MD02 and i made schedule agreement for the same and in ME38 it is showing open quantity 2000 but when i m going to see in ME2M then it must show 2000 as still to be delivered, but it is showing as 0.

plz help.

regards saurabh.