Dear Team,
Process is
1. PR is getting created thru Sales Order automatically.
2. PO is created for partial quantity. Say 50 qty out of 100.
3. Again when we created PO for remained quantity, system throws error that it is already partially ordered.So unable create PO.
Materials for PReq 10000170, item 00070, already partially ordered
Message no. 06249
Message was Not exist in config. I hv created that message with Warning message. But still Error exist.
Pls suggest
Hi,
I think you are talking of a Third Party PO, in which case the PR has been generated through Sale Order.
If you have partially ordered the material against the PR, then you will not be able to raise another PO with reference to the same PR.
What you can do is create another manual PR with Item category as S (Third Party) & account assignment S (Third Part) with PR document type as same which gets generated through sale order for balance quantity. This PR can be converted to PO & further cycle is same as that of Sale Order generated PR.
Regards,
Prashant Kolhatkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When manual PR is raised with account assignment of Sale Order, then Sale Order is not updated for the ordered quantity, but the COGS (Cost of Goods Sold) is updated in the sale order after GRN is posted. You can then raise invoice on Customer in the same way as that of normal Third Party Transaction.
You can try this solution on your backup / test server before implementing on Production enviroment.
Regards,
Prashant Kolhatkar
Hi,
if u are working in ECC 6.0 then
in spro --> environment --> system messages
here u can give this as error or warning !
put 00 06 249 as warning !
Also go to SE91, give messages class 06 and here go to 249....watch that this this is self explanintry is checked or not
as i have applied already this one !
Regards,
Pardeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i also faced the same problem. i tried the warning message solution but it did not work for me.
so we created some work around.
what we have done or made std process is like this.
if a sales order is created and the corresponding PR is generated in background.
pr is partially ordered then we will change the sales order quantity to ordered quantity and if required then add new line item in the same sales order.
this was accepted by our client. so you can try this.
regards,
Adwait Bachuwar
Edited by: adwait bachuwar on Nov 18, 2009 9:40 PM
Hi,
if u are working in ECC 6.0 then
in spro --> environment --> system messages
here u can give this as error or warning !
put 00 06 249 as warning !
Also go to SE91, give messages class 06 and here go to 249....watch that this this is self explanintry is checked or not
as i have applied already this one !
Regards,
Pardeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If are ordering the remaining qty for the same vendor then u can create one more line item in the existing PO by going in to change mode ME22N.
If u r ordering for the different vendor , then check whther they have defined any constraints while creating PR from SO , that it has to be ordered from same vendor.
And also check whether PR is associated with source of supply
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Which SAP version you are working with.
Please let me know.
Regards,
Anna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.