Workforce planning

Former Member
0 Kudos

I am getting the following message:

No requirements were found for the selection criteria

Message no. C#043

What can be wrong? I know it can be quite a lot of different reasons, but have not identified it yet.

Thanking you for input!

Accepted Solutions (0)

Answers (2)

Answers (2)

nitin_patoliya
Active Contributor
0 Kudos

1. Have you set the 'Capacity requirements' indicator in the 'Scheduling' block of the network header?

2.That there is work entered for the activity

-3.Check if the Other formula used for capacity category in the work center is filled or not. Test the formula with the values of the work used for the activity. For the PS system, only the forumula 'other formula' is relevant.

4 Check the control key used for the activity. If the control key of activity does not support any capacity requirements planning, the system does not calculate any capacity requirements.

5 Check the status of the activity. Is the activity technical closed or finally confirmed? Finally confirmed or technically closed activities have no longer any capacity requirements.

Check above option. It is always worth while to give T Code where you are checking.

With Regards

Nitin P.

former_member523116
Participant
0 Kudos

Hi,

May be the reason, you havn't check the capacitiy requirements or else check the workcenter wise.

Thanks a lot,

Gujju

Former Member
0 Kudos

If you havn't done it yet... try to activate your capacity req. from the builder or Planning board.

Edit u2192 Functions u2192 Activate

Capacities.

Nir