no itemziation exist fro material in plant

former_member604117
Participant
0 Kudos

when i run ck11n i get the error the no itemization exist from material in plant

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Goto Tarnsaction OKKN and check whether in Update Tab Itemization is selected or not. Select Itemization tab to display in CK11N.

Regards,

Sreekanth

former_member604117
Participant
0 Kudos

thanks

former_member604117
Participant
0 Kudos

thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

Itemization means, BOM & ROUTING.

Check whether BOM & ROUTING are created for the material for which you are trying to do Cost estimate.