Hi, Pls advise where we define opening period in spro for planning purpose?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Opening periods are setup in scheduling margin key.

Customize the same by following the path:

spro > Production > MRP > Planning > Scheduling and Capacity Parameters > Define Floats (Scheduling Margin Key)

Then assign the same in material master in MRP-2 view.

Regards,

Vivek

Former Member
0 Kudos

Hi, as i understand, schedue margin key is to show extra time and where is exact opening time is set? thank you.

Former Member
0 Kudos

YS,

It is the first column in the config given by Vivek. It is abbreviated "Op.Pd". Are you having a problem finding this config?

Or, are you saying that you are not clear about how SAP treats opening period?

Rgds,

DB49

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

The opening period is the time required by the MRP controller to convert the planned orders into purchase requisitions.

It is defined in scheduling margin key of material master which is maintained in 'MRP2' view.

For the MRP Run with "Create Purchase Requisition in opening period ", which means that the MRP creates preq at the time calculated as follows: Requested date - planned delivery time = opening period. Untill this moment MRP keeps them as planned orders.

Hope clear to you.

Regards,

R.Brahmankar