Hi, Pls advise where we define opening period in spro for planning purpose?
Hi,
Opening periods are setup in scheduling margin key.
Customize the same by following the path:
spro > Production > MRP > Planning > Scheduling and Capacity Parameters > Define Floats (Scheduling Margin Key)
Then assign the same in material master in MRP-2 view.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
The opening period is the time required by the MRP controller to convert the planned orders into purchase requisitions.
It is defined in scheduling margin key of material master which is maintained in 'MRP2' view.
For the MRP Run with "Create Purchase Requisition in opening period ", which means that the MRP creates preq at the time calculated as follows: Requested date - planned delivery time = opening period. Untill this moment MRP keeps them as planned orders.
Hope clear to you.
Regards,
R.Brahmankar