Hi experts,
I have one query. Process Order No. 6310000626 was using RM Neurobion 5000 Tablet, Batch L0600602, but then using the same number of Process Order, it replace with Neurobion 5000 Tablet, Batch L0600603. Inspection Lot No. 40000204626 remain open, but actually it was not used, because we use Insp Lot No. 40000205719.
The results recording has been carried out for the inspection lot 40000204626. Now the stock is lying in Qulaity Inspection stock. The Usage Decision is not made. So when I tried, it was not possible to delete the Inspection Lot and cancell the material document.
So how to cancell the GR posting and delete the Inspection lot.
Please help.
Regards
Brijesh
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
First do the stock posting only without giving UD code
Then reverse to the process order by MB31 with 102 mvt type, process order and stock type unrestricted use.
Save it. The materials will be moved to process order again.
Regards,
Alagesan M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi all,
Now the usage decision is made. The stock has moved to Unrestricted Use. After that through MB1B, i have moved the stock from Unrestricted use to Quality Inspection stock via 322 movement. I have done this after updating Inspection Type "08" in material master. And now when I try to do the GR posting reversal (102 movement), it is not happening. It gives the below error message.
Change the inspection stock of material TEST-FIN in QM only
Message no. QA495
Diagnosis
You want to make a stock posting to/from the inspection stock. This is not allowed for material TEST-FIN because the quality inspection control has been activated by QM.
The following cases can occur:
The inspection stock should be increased, although an inspection is not foreseen for the current goods movement
The inspection stock should be released, although you can only do this using the QM transactions.
System Response
You cannot carry out the stock posting.
Procedure
Check both the QM inspection setup data and the movement type for material TEST-FIN in the quality management view of the material master.
Exception:
If you post a return delivery to a vendor with reference to a purchase order, or cancel a goods receipt, the stock indicator from the order is proposed.
Check and modify this proposal as required.
The stock may have been transferred already and is therefore no longer in inspection stock.
Please help,
Regards
Brijesh
Dear as you said UD has been done and moved the stock to unrestricted if you want to reverse the GR(102) then you could
have reversed the inspection lot(UD reversal) by applying SAP note 175842 or user exit EXIT_SAPMQEVA_00 instead of
moving of stock through MB1B movement type 322.
So now clear the QI stock through UD which does 321 and move the stock to unrestricted then do UD reversal as i said above
to bring the stock back to QI then you do the MIGO cancelation(102).
Check and Revert.
Cheers
KK
Dear if you want to cancel the inspection lot then cancel that particular process order confirmation through CORS and MBST
transactions or you can cancel the of inspection lot from QA02 screen too go to Inspection lot > function> Cancel lot then
save it , and after that in qa32 screen you are able to see the system status LTCA means that inspection lot is cancelled.
Cheers
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.