cancel
Showing results for 
Search instead for 
Did you mean: 

Exception message 52 shown in MD04

Former Member
0 Kudos

Hi,

I have planned my FG using strategy 50.I maintained PIR's and ran MRP. But when I went and saw the requirements generated in MD04 a Exception message 52 (No BOM selected) is shown. Why is this Message generated.

Regard's,

Uday.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

check the valid start date of the BOM and the planned order start date.

Check and revert back.

Thanks,

JK

Former Member
0 Kudos

Hi Karthi,

BOM valid date is from 12/07/2011. For Planned order the date shown in MD04 screen is 01/07/2011. If I double click it as order start date as 29/06/2011 and order Finish date as 30/06/2011. What is the date shown on MD04 screen and these order start and finish dates..??

Please xplain me in detail.

regard's,

uday.

Former Member
0 Kudos

Hi,

In MD04 the date 01/07/11 is the availability date, the production dates (lead time in Materials master are in the planned orders { 29/06/2011 and order Finish date as 30/06/2011}.

So here the problem is the planned order is created when there is no BOM validity exist.

To overcome this adjust the demand in MD61 for next month or delete and recreate BOM will validy date from 01.06.2011.

Thanks,

JK

Former Member
0 Kudos

Hi Karthi,

You are correct. BOM validity date is different to the Planned order available date. Thanks for your response.

Regard's,

Uday.

Answers (0)