BT Method of Safety Stock Planning in SNP

Former Member
0 Kudos

Hi,

Could someone please let me know the BT method formula in SNP?

I tried everywhere but could not find accurate documentation on the same.

Regards,

Vinay Kalap

Accepted Solutions (1)

Accepted Solutions (1)

former_member492024
Active Participant
0 Kudos

Hello,

Check the documentation from the F1 Help below, it explains about all Safety Stocks methods, even BT:

Use

There are various safety stock calculation methods:

Standard methods

Extended methods

Standard Methods

You use these methods to define the amount of safety stock and the safety days' supply in a direct and simple manner. Both of these parameters can be defined as period-based or not period-based. You can define the parameters that are not period-based directly in the location product master (on the Lot Size tab page). You define the parameters that are period-based in interactive Supply Network Planning (SNP).

Period-based Not period-based

Safety stock MB SB

Safety days' supply MZ SZ

Maximum from both MM SM

Extended Methods

The system uses these methods to calculate period-based safety stock based on a forecast error and the service level specified. There are four different methods available depending on the lot-sizing procedure and service level chosen:

Reorder point method Reorder cycle method

Alpha service level AS AT

Beta service level BS BT

The alpha service level is event driven. Crucial here is the number of periods in which no shortfall quantities are expected. For example, if there is a service level of 90%, no shortfall quantities are expected in 90% of the periods.

The beta service level is shortfall quantity driven. It is calculated as follows: The expected fulfilled demand is divided by the expected total demand. For example, if the expected total demand is 100 pieces and a beta service level of 90% has been specified, the expected fulfilled demand is 90 pieces.

In the reorder cycle method, it is indicated that purchase orders can only be made for all t periods.

In the reorder point method, a purchase order is generated within the framework of SNP planning depending on stock level.

Dependencies

It is a prerequisite of the extended safety stock calculation methods that the uncertainties in the supply chain (referring to demand in different periods and locations as well as production and transportation times) are statistically independent from one another. It is also required that stock shortfalls are eventually delivered (backorder case).

In the case of the safety stock method MM, the SNP optimizer only takes account of independent demands, and dependent demands and distribution demands that result from fixed orders, since these demands and demand locations are already known before the optimization run.

Regards,

Michel Bohn

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi VInay,

I'm trying to use the method BT too, but it is too dificult to understand the values calculated at /SAPAPO/MSDP_SB.

It seems the forecast error and the historical data are not taken into account, only the RLT error and service level seems to be used.

Do you have any sign about the formulas used by /sapapo/msdp_sb?

Thanks a lot!