Hi All,
Can anyone explain the config that will be required on ECC / PI / SNC to send ROEMPROACT2 XML from ECC side and recevie the PAN XML successfully on the SNC side.
I already went through this link : but couldnt understand.
Also what transaction to use to check if the XML has been sent out successfully from the ECC system (Like we use WE05 for the Idocs)
Thanks,
Bharath
Hi Bharath,
In ECC you need to maintained the PI logical system in transaction SXMB_ADMIN.
In PI you need to mapped XML mapping <ECCLogical_system>|ProductActivtyNotification_Out|<SNC_Logical_System>
In SNC you need to maintain ProductActivityNotification_In XML configuration(By default this setting will be there) if it is not maintained then:
Go to SPRO>Supply Network Collaboration>Basic Settings>Processing Inbound and Outbound Messages>Process Types for Inbound Messages-->Assign Inbound XML Messages to Default Process Types
XML Message=ProductActivityNotification_Inbound
Process type=Supplier Collaboration.
Go to transaction code SXMB_MONI or SXI_MONITOR to check XML message in ECC.
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
4 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.