on 01-18-2012 9:27 AM
Hi,
We have four system landscape. We have already upgrade our DEV and ITT to EHP5.We still have to upgrade our UAT and prod to EHP5. When I see the transport queue on ITT system.I see all the transport that was imported on ITT before the upgrade is showing as "Does not match component version".
I can understand that the version before the upgrade was different so it should show that message.
I just wanted to check if this is normal or I need to make changes to TMS?
Regards!
Ravi
Hi,
You can do as follows:
Switch it off with parameter : SP_TRANS_SYNC = OFF
Procedure:
Call transaction STMS
Goto 'Systems Overview'
Double click <SID> you wish to add the parameter to
Goto 'Transport Tool' tab
Goto 'change mode'
Add SP_TRANS_SYNC to parameter column and OFF to value column
Save, activate and distribute
With Version SAP_BASIS 702 a new feature was added to the TMS system,
tp is now checking the component version of the transport which was
released and the component version of the system where the transport is
going to be imported. If there is a difference, this difference is
highlighted in the import queue (transaction stms_import) and if you try
to import the transport, the import will stop with a warning message
about the difference in the SAPCOMPONENT versions.
If you wish to by-pass with warning then you can choose 'Ignore invalid
Component version'.
Regards,
Aidan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please be aware that SAP does not recommend to switch off the
component version check in general.
I would advise though to leave it on and tick the relevant option
on a need basis only, once you have taken the warning into
consideration.
As reference for the parameter please see SAP notes:
#[1581638 |http://service.sap.com/sap/support/notes/1581638]SAP component checks no longer working in TMS
#[1577714 |http://service.sap.com/sap/support/notes/1577714]Transport requests in Check requirements phase
Regards,
Aidan
Hi Nicholas,
We are not doing any transport betweent the different release.I just wanted to check if its normal message that is being displayed,as we are in porcess of EHP upgrade and yet we stillh ave to upgrade UAT and Prod environment.
Also after the EHP5 do I have to live with this in my STMS queue or I can should deactivate it as Aidan suggested?
Regards!!
Ravi
User | Count |
---|---|
75 | |
9 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.