Restrict SNP safety stock planning scope

Former Member
0 Kudos

Hi All,

In ECC,we have the safety time indicator and safety time act. Coverage (MRP 2 view) to define whether the safety time is applicable to independent requirements or to all requirements during safety stock planning.

As the safety time indicator is not CIFed across to APO, how can we achieve/configure the same scenario in APO so that SNP safety stock planning considers days supply and only plans Independent requirements(PIR,sales order) 

Thanks in advance.

Cheers!

Sabareesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member453166
Participant
0 Kudos

Hi Sabareesh,

If this is the business requirement and you want to exclude dependent and distribution demand from the calculation of safety days' supply, then I'd recommend the following:

1. Create a new time-series key figure in which to populate the sum of forecast and sales orders (simple macro).

2. Modify the standard Safety Stock Macro which I've copied below to refer to the "Area" for the new key figure for planned demand, instead of what it generally refers to, which is total demand.  You can look at the existing standard SNP macro for Safety Stk/Reorder Point/Targt Stock Lvl in order to understand how to modify.

SAFETY_CALC('product' ; 'location' ; 'version' ; safety days' supply ; safety stock , key figure for planned demand )