on 10-04-2012 3:53 PM
Hi all,
I've got two SAP PI systems, QA and PROD.
I've got also two sld environments, one for QA and the other one for PROD. I have done a copy fro QA to PROD.
Now I want to deploy (via file) my integration scenarios from QA to PROD. I have defined transport groups in SLD PROD, but when I do the import of the file I've got this error:
Obligatory transport target for business system <SYSTEM>|<CHANNEL> not found in System Landscape Directory
I have seen several post about this topic, but no one help me.
Any Idea?
Regards.
Hi,
I had faced a similar situation, For this kind of an issue you need to define the SLD parameters and create business system for both the SLD's i.e. in both Quality and Production.since these are in two different environments. Hope that helps anyone facing a similar issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For the transport settings to take effect you need to restart the system. At least when transporting iFlows in NWDS.
SAP forgot to mention that restart is necessary in
1604679 - PI transport fails: "Obligatory transport target for business system not found"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to set up the Transport Target in SLD QAS for the relevant Business System, and set up the "Transport Source" in SLD PRD.
You have to obtain something that looks like:
QAS Sld
BS_QAS -> Transport Target BS_PRD
PRD Sld
BS_PRD -> Transport Source BS_QAS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Simone,
so as I read from your post, I have to register my SAP PI Production into QA SLD, in order to asociate productive sistems to the Integration Server in SAP PI Production, and then assing my business systems to that integration server and then define the transports targets.
Is that correct??
Hi,
as your business system is not correctly transported to PRD you are getting this error.
you need to have all three business systems in DEV,QA and PRD.
then in sld add the entries in your Business system --> Transport groups
like below:
For DEV target groups should be QAS and PRD
DEV -->QAS
PRD
For QAS source group should be DEV and target groups should be PRD
DEV-->QAS-->PRD
For PRD source groups should be DEV and QAS
DEV-->PRD
QAS
Regards,
Naveen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I only have QAS and PROD
But I've got two different SLD, one for QAS and the other one for PROD.
I have configured, for instance,
FCQCLNT100 as QAS and FCPCLNT100 as PROD in PRODUCTIVE SLD, and I have alse configured FCPCLNT100 as Target transport for FCQCLNT100.
I tried to import and I get this error:
Import failed because of business system transfer of object Communication Channel | FCQCLNT100 | CC_RECEPCION_IDOC: Obligatory transport target for business system FCQCLNT100 not found in System Landscape Directory
See error logs for details