hi everybody,

i've found some inconsistent data in our plmz table.

in my example there is one task list group 50051619. within table PLMZ for this task list group there are table entries for 2 plants: 1000 and 1001.

you can see this at this screenshot:

in table plko there is only one entry for task list group for plant: 1001

and nothing for plant 1000.

my first question:

1. how could this happen?

2. how can is solve this problem (correct the inconsistent table entries)?

best regards

chris

Accepted Solutions (1)

Accepted Solutions (1)

kiran_kumar179
Active Contributor
0 Kudos

Stromitzky,

See whether any of below SAP Notes useful to you

737422 - CA02/CA03: Display of invalid component assignment

658860 - Correction report: Adjust PLMZ w/ STAS for stand. networks

1326928 - Supplement to Note 310689

BR
KK

Chris_2311
Participant
0 Kudos

Thank you guys for your help