Hi,

I have 2 questions concerning commercial project management:

1- Do I have to Create a project first in SAP ERP "PS" or I can create a project in commercial project management direct?

2-Do I have to update my ERP system with any changes happens in commercial project management or these changes are updated automatically?

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Dear Allaa waked.

I'd like to answer as my experience.

1. CPM only can read project object that already made from ECC PS.

    You can assign 'CPM master Project' with 'ECC PS project'.

2.  Some data can read automatically to CPM when you change data from PS such as WBS or activities. but when you change some data in CPM, you should make BAdI implementations or configure 'Transfer to ECC' IMG to sync with ECC PS. It depedns on data that you wants.

Best Regards.

Kwangkyun Choi.

View solution in original post

1 REPLY 1

Former Member
0 Kudos

Dear Allaa waked.

I'd like to answer as my experience.

1. CPM only can read project object that already made from ECC PS.

    You can assign 'CPM master Project' with 'ECC PS project'.

2.  Some data can read automatically to CPM when you change data from PS such as WBS or activities. but when you change some data in CPM, you should make BAdI implementations or configure 'Transfer to ECC' IMG to sync with ECC PS. It depedns on data that you wants.

Best Regards.

Kwangkyun Choi.