on 07-02-2008 6:38 PM
Dear All,
We are getting the following error while transferring the PDS( BOM+ Routing+ Prod Version) from R3 to APO.
Error in APO: Unit of bucket consumption does not fit to dimens 073 /SAPAPO/CURTO
Just wondering If anyone has encountered this error.
APO Details:
The resource maintained on APO is a MULTI MIXED and both the Continuous and Bucket Dimensions are set to " No dimensions".
On the Time Continuous Capcity Tab, we havent maintained any dimension.
On the SNP Bucket Capacity, the Bucket Defn has been selected to " Maintain" and the period type is set as " Days" and the number of periods = " 1" and the Bucket Capacity dimensions are STK or PC.
R3 Details:
Routing: The UOM maintained is PC
Bom: The UOM maintained is PC
Checked all the other data.
Any pointers are appreciated.
Regards
Kumar
Hi All,
Just wondering If anyone could throw some pointers
Regards
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello there,
looks like you have firstly CIFed the PDS with different resource settings.
If you set in the resource SNP tab from "maintain" to "from continuous .." the error should dissapear.
Delete orders, delete PDS, set ressources right ("Maintain in SNP tab" ) and CIF PDS again
Regards Klaus